Shah Alam LRT3 line fault-free run expected to be completed by end-February

The Fault-Free Run (FFR) for the Shah Alam LRT3 project is progressing well, with all phases expected to be completed by the end of February, said Prasarana group chief operating officer (Strategy and Development) Prodyut Dutt.

He said the first batch, involving six trains, is 99 percent complete; the second batch, involving eight trains, is at 82 percent completion; while the third batch, also comprising eight trains, has yet to commence.

All three FFR phases...