Shipbuilder told to expedite work as LCS delivery slips further
As the timeline for the delivery of the navy’s littoral combat ship (LCS) slips further and further away, Defence Minister Khaled Nordin said he has told the shipbuilder to expedite work and ensure there will be no further delays.
The statement comes after the delivery of the first ship slated for December this year was pushed to April 2027 instead, and without its main anti-ship armament...
As the timeline for the delivery of the navy’s littoral combat ship (LCS) slips further and further away, Defence Minister Khaled Nordin said he has told the shipbuilder to expedite work and ensure there will be no further delays.
The statement comes after the delivery of the first ship slated for December this year was pushed to April 2027 instead, and without its main anti-ship armament.
Khaled (above) added that the expedited work will not wait for a royal commission of inquiry (RCI) to take place, Bernama quoted him as saying.
“The completion of LCS 1 is a separate matter and does not depend on the RCI. Otherwise, the ship would still not be completed.
“That is why we have asked the shipbuilder to speed up the work and ensure there are no further delays,” Khaled reportedly told the media in Kota Tinggi, Johor.
The minister said this when asked to respond to Pasir Gudang MP Hassan Abdul Karim’s call to “fast track” investigations into the LCS project with various enforcement agencies instead of waiting for an RCI to be formed.
Khaled also said the matter is best left to MACC and other authorities, and criminal action has already been taken against a former navy chief, who had also served as managing director of the shipbuilder Boustead Naval Shipyard Sdn Bhd.
/file/publisher-c1a3f893382d2b2f8a9aa22a654d9c97/2022/08/d9f21f93e659ae220b9c325c72314ecf.jpg)
The Bernama report did not identify the ex-naval officer, but it apparently refers to Ahmad Ramli Nor (above).
He had been charged with three counts of criminal breach of trust in relation to the LCS project in 2022, but was granted an acquittal not amounting to discharge (DNAA) last year after the Kuala Lumpur Sessions Court deemed him mentally unfit to stand trial.
As for procuring a new missile system to replace the naval strike missile (NSM), Khaled said the government is still negotiating with several shortlisted countries.
The procurement would not depend on the Budget 2027 allocation, as the ministry wanted to ensure that LCS 1 would not take too long to be fully equipped.
For now, he said the ship was equipped with surface-to-air missiles, anti-submarine warfare capabilities, and an electronic jamming system, with surface-to-surface missiles being the remaining capability yet to be installed.
/file/publisher-c1a3f893382d2b2f8a9aa22a654d9c97/2022/08/8493eb8a5114afacc665e0a3d08f4cfd.jpg)
The LCS programme signed in July 2014 was originally slated to deliver six ships from April 2019 to June 2023, at a cost of RM9.128 billion. These are sorely needed by the navy to rejuvenate its ageing fleet.
However, the project has since been hit with cost overruns, delays, allegations of financial wrongdoing, and Norway’s decision to revoke export licences for the NSM.
READ MORE: Fact check: Why did Norway ban missiles shipment to Malaysia?
The first ship, dubbed KD Maharaja Lela, was slated to be delivered in December this year. However, Khaled had told Parliament on Oct 7 that it would be delivered in April 2027 instead, without its anti-surface missiles.
The Auditor-General’s Report 2/2026 projected that problems procuring the NSM could mean the ship will not reach full operational capability until December 2035, after the main contract has already expired in April 2030.
“If LCS 1 is delivered on Aug 26, 2026, or on Dec 26, 2026, the ship will be handed over with incomplete training and armament,” it said.
The LCS was designed to carry eight NSM missiles as its main armament, capable of striking targets on land and at sea more than 200km away.
Its other anti-surface weapons comprise a 57mm dual-purpose gun and two 30mm autocannons. Both have substantially less range and firepower than the NSM.
READ MORE: KINIGUIDE | A littoral dive into the navy's RM9b LCS scandal
Not one UMNO politician has been charged for the massive leakage including the tale of the 2 wives. A totally ignored PAC report into the fiasco. Khaled making bold assertions against the Norwegian supplier without revealing the true cancellation clauses. Billions wasted on ships that will never fire long range missiles in anger on any other country. What a complete disaster the whole project is and not one single prosecution.
The Littoral Combat Ship (LCS) scandal originated when the Malaysian government, under then-Prime Minister Najib Razak, officially awarded the RM9.13 billion project to Boustead Naval Shipyard Sdn Bhd (BNS) in 2011. It has been 15 years, and now we are reading that even the first ship is struggling to be delivered on time. Only in Malaysia have we always observed this kind of STUPIDITY! Is technology the latest and most advanced, or is it 20 years behind? But Bolehland will pay for backward technology.
This kind of things can only happen in Bolehland. The govt is not strict to impose penalties for late delivery. If they do their job well, we can assure the contractors will follow and adhere to the clause of the contract. Delays caused money and their profit margin, so they will be serious in their obligation and deliver on time or earlier.
Report this comment
/file/publisher-c1a3f893382d2b2f8a9aa22a654d9c97/2026/05/d9ae1c0e21e17f5f25fb2a9266f32fc1.jpg)

/file/publisher-c1a3f893382d2b2f8a9aa22a654d9c97/2022/08/d67fe8b9956d4604ab2dc42be01344f2.jpg)
/file/publisher-c1a3f893382d2b2f8a9aa22a654d9c97/2026/05/36c75c0266f3a2922a85214a90c732d7.jpg)
/file/publisher-c1a3f893382d2b2f8a9aa22a654d9c97/2025/06/889f4a2fca1413a4ea89ad1da3e9b79d.jpg)
/file/publisher-c1a3f893382d2b2f8a9aa22a654d9c97/2026/01/365813e3d89d0e861690a5c371636a56.jpg)
Are you sure you want to delete this comment?
This action cannot be undone.